Computationally Optimised Manpower Rosters for Airline Short-Term Layover Maintenance.
Date
2014-08-18
Authors
Wilson, Neil David.
Journal Title
Journal ISSN
Volume Title
Publisher
Abstract
Abstract
Introduction: Short-term layover maintenance activities at an airline base generally involve the execution of significant numbers of high-frequency, short-duration routine inspections in between flights on aircraft that are deployed to ongoing flight operations. The problem of scheduling labour supplies for this type of maintenance activity requires an operations manager to consider issues such as the number of scheduled flights each day, the timing constraints for the tasks that must be implemented on aircraft that are departing from or arriving at the base of operations, the employee skills and certifications that are needed to implement the required maintenance actions, as well as the potential for the planned flight schedule and associated maintenance schedule to be disrupted by unforeseen events such as flight delays. Published literature in the operations research subject
area of ‘personnel scheduling’ covers a range of computational and mathematical techniques that can be adapted to solve or optimise this type of scheduling problem. This study has explored whether there is a significant knowledge gap between state-of-the-art developments in published research in this subject area and practical application at aircraft maintenance organisations on the African continent. Furthermore, the study has sought to establish whether computational models for the optimisation of an airline’s short-term layover maintenance labour resources that are based on a fixed flight schedule and thus a fixed task demand profile are sufficiently robust to the effects
of flight schedule disruptions (e.g. delays) that occur routinely in real-life operations to support their
practical application.
Methods: A case study method has been employed in this study. In this regard, a case airline
company based in Johannesburg, South Africa (with an in-house maintenance division) has been
used for data collection purposes and for the implementation and testing of an experimental labour
scheduling model for the short-term layover maintenance staffing problem. This labour scheduling
model has been developed by adapting modelling concepts and techniques from contemporary
operations research literature to the case setting. Initially, the experimental model has been used
to generate an optimised staff roster for short-term layover maintenance activities under the ideal
condition of 100% on-time performance of the case airline’s flight schedule. This optimised roster
has then been compared to the existing staff roster and associated labour planning model that are
in use at the case organisation for the given category of maintenance activity. Performance criteria
such as total direct labour costs and the stability of each staff roster have been considered in this
comparison. Following on from the initial computational modelling exercise, the optimised staff
roster has then been subjected to sensitivity testing in a simulation environment in order to assess
its robustness in scenarios where the input flight schedule and associated task demand profile for
short-term layover maintenance activities is disrupted from the original plan. To ensure high levels
of realism, schedule disruption profiles based on actual flight operations records in the case setting
have been used in this testing process.
Page III
Results: The initial study results show that the experimental model for the short-term layover
maintenance labour scheduling problem uses 33% fewer AMEs and 48% fewer rostered manhours
to meet the service demands of the case airline under fixed flight schedule conditions than the
equivalent labour force specified by the organisation’s existing labour planning model. However, it
has been noted that a significant portion of this resource saving relates to conservative demand
modelling by the case organisation, particularly with regards to the quantities and standard time
inputs that have been imposed for after-flight checks in the organisation’s existing planning model.
Adjusting for these conservative inputs, it has been shown that the experimental model provides a
22.0% reduction in rostered manhours and associated labour costs in comparison to a modified
version of the case organisation’s existing model, but with no reduction in the number of AMEs
employed. Although not as substantial as the original finding, this more realistic outcome remains
positive from the perspective of the operations manager and it has been estimated that associated
savings in direct labour cost savings could amount to almost 1.3 million rand per annum. The
robustness testing of the output labour roster from the experimental labour scheduling model has
also yielded satisfactory results. In this regard, the output roster has been shown to require only
3.75 manhours of unplanned AME overtime in order to manage the modified demand profiles for
short-term layover maintenance tasks relating to simulated flight schedule disruptions over a 20
day testing period in the case setting. This level of unplanned overtime adds only 0.41% in
supplementary charges to the case organisation’s labour bill at an overtime rate of 1.5 times the
normal AME labour rate. Furthermore, no requirements for AME callouts and no conflicts in terms
of induced flight delays due to missed maintenance tasks have been identified over the robustness
testing period. These findings suggest that the impacts of unplanned flight schedule disruptions on
the experimental labour planning model are largely insignificant.
Conclusions: The outcomes of the study support the assertion that a significant knowledge gap
exists between state-of-the-art research in the subject area of personnel scheduling and practical
application at African-based aircraft maintenance organisations. In addition, preliminary evidence
has been obtained to suggest that computational models for the optimisation of short-term layover
maintenance labour resources at an airline under fixed flight schedule conditions are sufficiently
robust to the effects of schedule disruptions to support their practical application. However, these
conclusions must be considered within the context of the case-based research methodology that
has been employed. In this regard, it is recommended that further research be conducted in order
to examine the transferability of research findings at the case organisation to a broader population
of aircraft maintenance organisations on the African continent. Furthermore, it is acknowledged
that only a limited scale of robustness testing has been implemented in this study. As a result,
additional robustness testing over an expanded set of test days is recommended as an extension
to the study.
Description
MBA 2013
Keywords
Airlines -- Personnel management, Airlines -- South Africa -- Management, Manpower planning .