Reliability improvement of the boiler-coal processing plant in eskom using reliability centred maintenance principles

dc.contributor.authorSibanda, Ray Takudwanashe Jones
dc.date.accessioned2018-10-12T13:32:36Z
dc.date.available2018-10-12T13:32:36Z
dc.date.issued2016
dc.descriptionA research report submitted to the Faculty of Engineering and the Built Environment, University of the Witwatersrand, in partial fulfillment of the requirements for the degree of Master of Science in Engineering in Mechanical Engineering by course work and research report. 25 October 2016en_ZA
dc.description.abstractThe objective of this report is to compare the existing maintenance methods in Eskom to RCM and then test the applicability of RCM in improving boiler reliability. Firstly, a comparative study was conducted on different RCM methods and the RCM method to apply selected and compared to the Eskom’s initiatives. The RCM method is piloted to a sample system and the results are compared with those from the current Eskom’s initiatives. The biggest change due to the RCM analysis was the way to document the results of the RCM process as compared to the current practice. It was also found that intervals between maintenance tasks proposed by the RCM study are different from the intervals currently used. In conclusion, the report recommends that the RCM results be used as a guide for continuous improvement in order to fill in gaps that are crucial in determining reliability goals.en_ZA
dc.description.librarianMT 2018en_ZA
dc.format.extentOnline resource (116 leaves)
dc.identifier.citationSibada, Ray Takudzwanashe Jones (2016) Reliability improvement of the boiler - coal processing plant in Eskom using reliability centred maintenance principles, University of the Witwatersrand, Johannesburg, <http://hdl.handle.net/10539/25784>
dc.identifier.urihttps://hdl.handle.net/10539/25784
dc.language.isoenen_ZA
dc.subject.lcshEskom (Firm)
dc.subject.lcshCoal--Combustion
dc.subject.lcshCoal-fired furnaces
dc.titleReliability improvement of the boiler-coal processing plant in eskom using reliability centred maintenance principlesen_ZA
dc.typeThesisen_ZA

Files

Original bundle

Now showing 1 - 1 of 1
No Thumbnail Available
Name:
Ray Takudzwane Jones Sibanda.pdf
Size:
4.59 MB
Format:
Adobe Portable Document Format
Description:

License bundle

Now showing 1 - 1 of 1
No Thumbnail Available
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description:

Collections