Key challenges faced by main contractors in coordinating the works of their subcontractors: a case study of Kusile power station project
No Thumbnail Available
Date
2019
Authors
Noganta, Abongile
Journal Title
Journal ISSN
Volume Title
Publisher
Abstract
Coordination is a crucial function in the management process of interdependent parties and
their activities. In major construction projects, where there are manifold participants; the
contractor is faced with the challenge of coordinating the interdependent subcontractors’
tasks and subtasks in ensuring that quality standards, time and cost requirements are met and
ultimately project success is achieved. Lack of coordination of subcontractors’ works by the
main contractors is one of the causes of deviations from project goals such as delivering a
quality project within time and cost. This research is directed at identifying the key
challenges that main contractors face when coordinating the subcontractors’ works in major
construction projects and how they overcome these challenges. Kusile Power Station was
chosen as a case study for this research because it is a large project whereby the problem was
observed by the researcher. This case was strategically selected because of the numerous
contractors (at different levels) working at the peak stage of the project. In-depth interviews
were held with four main contractors’ representatives dealing with coordination at the Kusile
Power Station Project. These four main contractors were selected based on the scope they are
contracted to do, size of the company, and the number of subcontractors they manage and
were responsible for. The four main contractors interviewed had 46, 8, 9 and 6 subcontractors
respectively. 32 challenges were identified and grouped into 7 seven distinct groups. The key
conclusions from the research data analysis was that resource handling (issues), clashes/
changes in designs/ drawings, and access issues are the three key coordination challenges
faced by main contractors at the Kusile Power Station Project. To overcome these major
challenges, the contractors perform & make use of resource scheduling, two/ three week look
ahead, and site walks. It is recommended that a similar study he done in another major project
to uncover other means of dealing specifically, with the three key challenges